Count business days between two dates in SQL
SLA clocks and delivery estimates count working days only. Weekends are computable; holidays need a lookup table.
The task
Generate one row per calendar day between the dates, keep the weekdays, and count them.
The snippet
Written for SQL Server. Versions for PostgreSQL are under Variations.
DECLARE @start_date DATE = '2026-03-02', @end_date DATE = '2026-03-31';
WITH days AS (
SELECT @start_date AS d
UNION ALL
SELECT DATEADD(DAY, 1, d) FROM days WHERE d < @end_date
)
SELECT COUNT(*) AS business_days
FROM days
WHERE (DATEPART(WEEKDAY, d) + @@DATEFIRST - 1) % 7 NOT IN (0, 6)
OPTION (MAXRECURSION 0);
So funktioniert es
The recursive CTE walks one day at a time from start to end, and the WHERE drops Saturdays and Sundays: adding @@DATEFIRST to DATEPART(WEEKDAY) makes Sunday 0 and Saturday 6 whatever the session's DATEFIRST is, and unlike DATENAME it does not depend on the session language. March 2026 has 22 weekdays. MAXRECURSION 0 removes the 100-level default cap so long ranges work. For holidays, add AND d NOT IN (SELECT holiday_date FROM holidays).
Variations
PostgreSQL
PostgreSQLSELECT COUNT(*) AS business_days
FROM generate_series(DATE '2026-03-02', DATE '2026-03-31', interval '1 day') AS g(d)
WHERE EXTRACT(ISODOW FROM d) < 6;
Questions that come up
Does this count the start date?
Both queries count both ends: the recursion emits the start date and keeps going until it has emitted the end date, and generate_series includes its upper bound. For a 'days until' style count that excludes the start, begin the series one day later; decide the convention once and document it.
Keep reading